Grand Street Guild

Last updated

10:00pm Oct 8, 2024

Active apartment installs: 230

460: 87
410: 68
131: 75

Total active installs

2 community computers
9 access points (outdoor, community, laundry)
221 apartments

232 Total

Community room computers

Laundry installs (active)

131, 410, 460

All floor raceways and fiber have been completed

Fiber bypass August 2023

Fiber is now running as before through underground conduits. The fiber bypass has been removed and the POE sealed

Recent apartment speed tests

Ethernet-

Speeds are now typically around 900 Mbps down, 750 Mbps up

Recent ethernet test-
https://www.speedtest.net/result/14527726621

Wifi-

New installs using the new Ubiquiti WiFi6 ONT, combined fiber ONT and wifi router, with speeds close to 700Mbps.

All new installs and many older installs are now WiFi6 devices. We’ve been gradually replacing the original Locos with Wifi6 as these require less support

Recent WiFi test-
https://www.speedtest.net/result/13730130631

Active Backhaul

Fiber from 131 Broome to 111 8th POP exiting in building. DE-CIX IXP and Pilot transit

Backup connections

  • 10 Gigabit wireless (Siklu) to 303 Vernon.
  • 1 Gigabit wireless (AF24) to SN1

Planned upgrades

September 2024 we will be upgrading the router at 111 8th Ave which will help with multiple gigabit connections in the new 165 Broome Street building.

Fiber Install Leaders

Sean